MATTER:
Dispute resolution of the thermal power project EPC Contract, valued at up to 438 million USD (2017)
CLIENT:
A subsidiary of Vietnam Electricity Group
BACKGROUND:
The Client, a subsidiary of Vietnam Electricity Group, is the Employer of a thermal power plant project in the North (“Thermal Power Plant”), having 2 machine assemblies (machine assembly No. 3 and No. 4) with a power sum of 600MW/year, of which investment principle approval was approved by the Prime Minister in 2003 and of which construction investment project was approved in 2006. In November 2006, the Client signed an EPC Contract with a Chinese Contractor (“Main Contractor”) on the design, execution, procurement, installment, and test on completion of the Thermal Power Plant, the contract price being of 420 million USD, time for completion (PAC) of the machine assembly No. 3 was agreed to be in February 2010 (corresponding to 32 months of execution) and the machine assembly No. 4 was agreed to be in July 2010 (corresponding to 37 months of execution). The financial funding arrangement to pay for the EPC Contract was consisting of a 85% import-export financing loan from a Chinese Bank (“Financing Bank”) and 15% of equity.
In April 2007, the Client and the Financing Bank signed a commercial loan contract allocating an amount of nearly 356 million USD to pay 85% of the EPC Contract price which had been signed with the Main Contractor. However, until October 2010, such the loan agreement took effects. Therefore, in July 2011, the Client and the Main Contractor signed an Addendum to amend the EPC Contract, accordingly amending (i) the date of resume of the project execution: June 1, 2011; (ii) Issuance of PACs for machine assembly No. 3 by December 31, 2012, at the latest; (iii) Issuance of PACs for machine assembly No. 4 by May 31, 2013, at the latest; (iv) the Contract price increased to USD 438 million (with the gap being of USD 18 million). This addendum will be effective upon fully satisfaction of the followings: (i) this addendum is executed by the parties; (ii) this addendum is approved by the authorities (“the Addendum”).
However, the completion of the Project was behind the agreed schedule, the PAC issuance date of machine assembly No. 3 was nearly 2 years behind the schedule as agreed by the provisions of the EPC Contract (Machine assembly No. 3 was actually granted to the PAC on January 1, 2014).
In 2017, both parties were proceeding the procedures for payment and finalization of the EPC Contract, the Client claimed the Main Contractor that the time for completion was behind the schedule and asked the Main Contractor to pay Liquidated Damages of 5% of the EPC Contract price. The Main Contractor made an encounter claim that due to the delayed approval of the Addendum, the Main Contractor shall be entitled to claim for an extension of the time for completion under the EPC Contract and claim the Client to pay for costs and expenses incurred during pending the approval of Vietnam authorities to commence all on-stie execution activities.
The Client appointed ATIM LAW FIRM as their legal advisor to thoroughly review the EPC Contract and other supported documents and to advise the Client to respond the Main Contractor's claims on additional expenses and extension of time for completion.
LEGAL ISSUES:
The Main Contractor’s claim on extension of time for completion with the reason that the Employer was delayed in obtaining approvals of the Vietnamese authorities for the Addendum and failed to provide evidences proving that financial arrangements has been available for payment under the EPC Contract. In this regard, ATIM LAW FIRM found several legal issues that the Client should pay attention to as follows:
SOLUTIONS:
ATIM LAW FIRM's lawyer reviewed the EPC Contract and other related documents, along with the study of laws and regulations, opined the Client on its advantages and disadvantages in dealing with the Main Contractor's claims and consulted how to build arguments to protect the Client’s benefit against those claims, more specifically as follows:
RESULTS:
ATIM LAW FIRM delivered the advice and helped the Client to develop arguments and determine resolution against the Main Contractor’s claims and the Main Contractor agreed with these resolutions